The Design Monitoring Framework (DMF)

Output
Performance Indicator
Key Activities with Milestones
Activities
Target (PAM)
Target (OWP)
IAs
Due Date
Baseline 2016
2017
2018
2019
2020
2021
2022
2023
1A
1a. Hydro-meteorological stations Installed and repaired/improvement.
1.1 Improve hydro-meteorological observations, data management, and processing [KNS].
G1A1 (3Cis)
18 AWLR, 4 AWS, 12 upgrade MRS to AWS.
21 AWLR, 4 AWS, 4 MWS, 3 TWL-EWS, 1 CCTVs, 1 ADCPs & structures, computer server & modeling, videotron.
MPWH, CS01
Q1 2022
15 AWLR (8 damaged, 2 inactive), 23 rainfall stations (7 damaged).
CS01 mobilization.
Rationalization study.
Finalized rationalization study.
Preparation of bidding document.
Bidding on 10 Sep 2021. Re-bidding on 28 Dec 2021.
Contract award on 21 April 2022 - 16 Dec 2022. Physical progress was 71.20% on Dec 2022.
Constructed/Install: 1 CCTVs, 1 ADCP & structures, computer server & modeling, Videotron. COMPLETED on Jan 2023.
1A
1a. Hydro-meteorological stations Installed and repaired/improvement.
1.1 Improve hydro-meteorological observations, data management, and processing [KNS].
G1B1 (Ambon)
18 AWLR, 4 AWS, 8 upgrade MRS to AWS.
4 AWLR, 2 Telemetric ARR, 2 Manual RR, 2 AWS, 2 Manual AWS, 7 set 2CCTV, 25 HT.
MPWH, CS01
Q1 2022
16 water level gauges (9 damaged).
CS01 mobilization.
Rationalization study.
Finalized rationalization study.
Preparation of bidding document.
Bidding on 10 Sep2021. Re-bid on 21 Oct 2021. Contract signed on 8 Dec 2021.
Installment: 4 AWLR, 2 Telemetric ARR, 2 Manual RR, 2 AWS, 2 Manual AWS, 7 set CCTV, 25 HT. COMPLETED on Dec 2022.
1A
1a. Hydro-meteorological stations Installed and repaired/improvement.
1.1 Improve hydro-meteorological observations, data management, and processing [KNS].
G1B2 (Ambon)
AWLR stations, ARR stations, AWS, and control building.
AWLR stations, ARR stations, AWS, and control building.
MPWH, CS01
Q1 2022
42 rainfall stations (13 damaged), 8 climate stations (6 damaged).
CS01 mobilization.
Rationalization study.
Finalized rationalization study.
Preparation of bidding document.
Bidding on 10 Sep2021. Contract signed on 22 Oct 2021.
Constructed: AWLR stations, ARR stations, AWS, and AWS-station. COMPLETED on Dec 2022.
1A
1b. Flood models calibrated, flood hazard maps prepared, and flood early warning systems operational in the selected RBTs.
1.2 Develop and calibrate hydrological and flood models, and prepare flood maps [GCD].
Flood Prone (3Cis)
MPWH, CS01
Q1 2022
FLOOD PRONE and FLOOD MODELLING of 3Cis RBT have COMPLETED on Mar 2020.
1A
1b. Flood models calibrated, flood hazard maps prepared, and flood early warning systems operational in the selected RBTs.
1.2 Develop and calibrate hydrological and flood models, and prepare flood maps [GCD].
G1A2 (3Cis)
FF-EWS
FF-EWS
MPWH, CS01
Q1 2022
CS01 mobilization.
Rationalization study.
Finalized rationalization study.
Preparation of bidding document.
Draft of Bidding Document.
Start bidding on 1 Oct 2022 of FF-EWS. Target contract on Jan 2023.
Contract signed on 15 May 2023. The FFEWS BBWSC3 application was developed. It is available at https://c3-ffews.sda.pu.go.id/.
1A
1b. Flood models calibrated, flood hazard maps prepared, and flood early warning systems operational in the selected RBTs.
1.2 Develop and calibrate hydrological and flood models, and prepare flood maps [GCD].
Flood Prone (3Cis and Ambon)
MPWH, CS01
Q1 2022
FLOOD PRONE and FLOOD MODELLING of Ambon-Seram RBT have COMPLETED on Mar 2020.
1A
1b. Flood models calibrated, flood hazard maps prepared, and flood early warning systems operational in the selected RBTs.
1.2 Develop and calibrate hydrological and flood models, and prepare flood maps [GCD].
G1B3 (Ambon)
FF-EWS
FF-EWS
MPWH, CS01
Q1 2022
CS01 mobilization.
Rationalization study.
Finalized rationalization study.
Preparation of bidding document.
Draft of Bidding Document.
Start bidding on 10 Nov 2022 of FF-EWS.
Contract signed on 26 June 2023. The FFEWS BWSM application was developed. It is available at https://psih3bwsmaluku.com/ffews/.
1A
1c. FRMPs for the selected RBTs endorsed by RBT basin coordination forums.
1.3 Prepare FRMPs for selected river basins [GCD KNS].
FRMP Prepared
8 FGD
8 FGD
MPWH, CS01
Q2 2020
Implementation of LIDAR mapping, Flood Modelling and Flood Prone mapping.
IOL, Social Economic Survey and vulnerability analysis, public consultation and discussion.
Draft FRMP document finalization and discussion with stakeholder.
Synchronization FRMP with regional development plan and implementation. FRMP to be submitted to TKPSDA.
Submitted to TKPSDA in January 2023.
1A
1c. FRMPs for the selected RBTs endorsed by RBT basin coordination forums.
1.3 Prepare FRMPs for selected river basins [GCD KNS].
FRMP Submitted
MPWH, CS01
Q2 2020
The draft FRMP document is being finalized.
1A
1c. FRMPs for the selected RBTs endorsed by RBT basin coordination forums.
1.3 Prepare FRMPs for selected river basins [GCD KNS].
FGD by stakeholders
4 districts
4 districts
MOHA, CS06
Q2 2020
Preparation of FRMP in Serang District.
Guidance and TOR prepared by CS06.
Regional FRMP preparations to be endorsed by local governments.
Under the process of endorsement by the local government.
1B
1d. Gender-sensitive flood hazard vulnerability, risk, and emergency response mapped and hazard categories zoned in flood risk areas of selected RBTs.
1.4 Prepare flood information bulletins, news, and activities jointly with BNPB [GEM].
Flood management related information and publication materials.
Quarterly bulletin
Quarterly bulletin
MPWH, MOA, MOHA
1. PIB by MPWH 2. Published bulletin information by BPBD. 3. Public information through MOA website.
1. PIB and video drone of construction works through YouTube by MPWH. 2. Published bulletin information by BPBD. 3. Public information through MOA website.
1. PIB and video drone of construction works through YouTube by MPWH. 2. Published bulletin information by BPBD. 3. Public information through MOA website.
1. PIB and video drone of construction works through YouTube by MPWH. 2. Published bulletin information by BPBD. 3. Public information through MOA website.
1. PIB and video drone of construction works through YouTube by MPWH. 2. Published bulletin information by BPBD. 3. Public information through website and TVRI dialog by MOA.
1B
1d. Gender-sensitive flood hazard vulnerability, risk, and emergency response mapped and hazard categories zoned in flood risk areas of selected RBTs.
1.4 Prepare flood information bulletins, news, and activities jointly with BNPB [GEM].
Gender-sensitive consultation and public awareness.
Workshops
Workshops
MPWH, TKPSDA, CS01, CS02
Preparation of TOR and budgeting for workshop.
1B
1d. Gender-sensitive flood hazard vulnerability, risk, and emergency response mapped and hazard categories zoned in flood risk areas of selected RBTs.
1.4 Prepare flood information bulletins, news, and activities jointly with BNPB [GEM].
Flood hazard vulnerability maps and flood risk maps.
MPWH, CS01
Flood hazard maps developed.
Flood vulnerability maps developed.
Flood risk maps developed.
BPBD has developed maps of Flood Hazard, Flood Vulnerability, and Flood Risk in Serang, Pandeglang, Lebak, and Ambon.
1B
1e. Guidelines for the linkage of flood hazard zoning to spatial plans, land use management regulations, and building regulations and development endorsed by provincial and district governments.
1.5 Establish localized flood early warning system, and communication system [GCD, KNS].
Flood emergency simulation.
4 districts
4 districts
MOHA, CS06
Q4 2022
Training/Simulation on Emergency Response Mechanism in Serang District.
Training/Simulation on Emergency Response Mechanism in Serang and Lebak District.
Training/Simulation on Emergency Response Mechanism in Serang District.
Training/Simulation on Emergency Response Mechanism in Ambon.
Serang in 2021, Lebak in 2022, Pandeglang in 2022, Ambon in 2022.
1B
1f. Women account for at least 20% of those trained in flood risk assessment and analysis, CBFRM prioritization, and implementation of locally appropriate FRM measures.
1.6 Support institutional strengthening, planning, and coordination of provincial and district local disaster management, meteorology, public works, land, social, and forestry agencies [GCD, GEM].
Including 20% women.
20%
20%
MOHA, CS06
Q3 2019
The establishment of PMU and PIU in Serang, Pandeglang, Lebak, Ambon, and Maluku were completed in 2018.
Based on the ADB Mission in July 2019, it was agreed to establish a PIU at the Environment and Solid Waste Agency in Ambon.
The PPIU of Environment and Solid Waste Agency in Ambon was established. Banten, Women 27% ON TRACK. Maluku, Women 28% ON TRACK.
Maluku, Women 39% ON TRACK.
Maluku, Women 33% ON TRACK.
Women's involvement is 33.27% (ON TRACK).
2A
2c. 246 farmers groups trained on sustainable agricultural practices and watershed management.
Selection of farmer groups and candidate location.
Verification and validation.
246 farmer groups
246 farmer groups
MOA, CS05
Q4 2019
Total (32): Serang (0), Lebak (32), Pandeglang (0).
Total (47): Serang (24), Lebak (13), Pandeglang (10).
Total (77): Serang (24), Lebak (14), Pandeglang (39).
Total (117): Serang (34), Lebak (44), Pandeglang (39).
Total (132): Serang (68), Lebak (45), Pandeglang (19).
Land Construction: 305 FGs. Land Optimization: 139 FGs. Total: 444 FGs.
2A
2d. 6,150 ha of land with improved management.
2.6 Prepare programs for soil and water conservation in village and agricultural lands [GCD, GEM].
Land Conservation
4.450 ha
4.450 ha
MOA, CS05
Q4 2019
7 land conservation packages, consisting of Organic Fertilizer Production Business.
Total 23 (825 ha): Serang 0 (0 ha), Lebak 14 (350 ha), Pandeglang: 9 (475 ha).
Total 14 (855 ha): Serang 14 (855 ha), Lebak 0 (0 ha), Pandeglang 0 (0 ha).
Total of 914 ha. Serang 18 (), Lebak 45 (), Pandeglang 14 ().
Total 77 (1,314 ha): Serang 18 (), Lebak 45 (), Pandeglang 14 ().
Total area: 7,625 ha. Serang (1,125 ha), Lebak (4,450 ha), Pandeglang (2.050 ha). Total trees: 331,145.
2A
2d. 6,150 ha of land with improved management.
2.6 Prepare programs for soil and water conservation in village and agricultural lands [GCD, GEM].
Land Optimization
1.700 ha
1.700 ha
MOA, CS05
Q4 2019
Total 203 ha: Serang (70 ha), Lebak (75 ha), Pandeglang (40 ha). Farm roads: Lebak (20).
Total 26 ha: Serang (26 ha), Lebak (0), Pandeglang (0). Farm roads: Serang (5), Lebak (10).
Total 396 ha: Serang (116 ha), Lebak (210 ha), Pandeglang (70 ha). Farm roads: Serang (20).
Total 180 ha: Serang (), Lebak (180 ha), Pandeglang ().
Total area: 3,475 ha. Serang (1,425 ha), Lebak (1,125 ha), (Pandeglang: 925 ha). Total trees: 59,763 (87.75% from OWP). Total farm roads (106). Serang (33), Lebak (43), Pandeglang (30).
2A
2d. 6,150 ha of land with improved management.
2.6 Prepare programs for soil and water conservation in village and agricultural lands [GCD, GEM].
Participatory Construction
FTC (3), Ponds (28), Village irrigations (4810 ha), Irrigation pumps (36), Micro dams (30), Infiltration wells (44).
MOA, CS05
Q4 2019
Lebak (32): FTC (1), Ponds (2), Village irrigation (14), Pump irrigation (6), Micro dams (6), Infiltration wells (3).
Serang (24): Village irrigation (12), Pump irrigation (7), Micro dams (5). Lebak (13): Ponds (3), Pump irrigation (3), Micro dams (3), Infiltration wells (4). Pandeglang (10): Ponds (5), Pump irrigation (2), Micro dams (3).
Serang (24): Village irrigation (20), Micro dams (4). Lebak (14): Ponds (4), Pump irrigation (7), Micro dams (3). Pandeglang (42): Ponds (6), Village irrigation (19), Pump irrigation (4), Micro dams (5), Infiltration well (8).
Serang (41): FTC (2), Ponds (5), Village irrigation (19), Micro dams (4), Infiltration wells (11). Lebak (48): Ponds (2), Village irrigation (34), Micro dams (10). Pandeglang (40): Ponds (5), Village irrigation (23), Micro dams (12).
Serang (3): FTC (1), Ponds (2). Lebak (26): FTC (1), Micro dams (7), Village irrigtion (18). Pandeglang (1): FTC (1).
Total Participatory Construction (322): FTC (6) Ponds (34) Village irrigation (4,975ha/160) Pump irrigation (31) Micro dams (65) Infiltration wells (26)
2A
2d. 6,150 ha of land with improved management.
2.6 Prepare programs for soil and water conservation in village and agricultural lands [GCD, GEM].
Including 10% women
10% women
10% women
MOA, CS05
Q4 2022
Out of 8,011 farmers, 1,144 are female farmers (14.28 %).
Training programs for FGs have been conducted: 711 women farmers out of 1515 farmers (46,93%) (GAP Target 4). Training for watershed rehabilitation and management conducted: 240 women farmers out of 464 farmers (51,72%) (GAP Target 5).
2B
2a. Flood protection infrastructure rehabilitated or upgraded as per FRMPs developed.
2.7 Implement watershed rehabilitation activities [GEM].
Small-infrastructure
Slope Reinforcement (30), Slope reshaping (30).
Pond (25), Retaining Wall (113), Slope Reshaping (37), Bio-engineering (2).
MOHA, CS06
Q2 2020
Lebak: Retaining wall (7) + Supervision (1), Ponds (10), Participatory planning (4). Pandeglang: Slope Reshaping (8), Participatory planning (4).
Serang: Ponds (2). Lebak: Retaining wall (15), Ponds (4). Pandeglang: Retaining Wall (37), Slope Reshaping (24), Supervision (10). Ambon City: Retaining Wall (10). Maluku Province: Retaining Wall (3), Bio-engineering (2).
Serang: Ponds (1). Lebak: Retaining wall (10), Ponds (7). Pandeglang: Retaining Wall (21), Supervision (13). Ambon City: Retaining Wall (8). Maluku Province: Retaining Wall (3), Bio-engineering (2).
Total construction (174): Ponds (24) Retaining Wall (114) Slope Reshaping (32) Bio-engineering (4) Participatory Planning (8) Supervision (24)
2C
2a. Flood protection infrastructure rehabilitated or upgraded as per FRMPs developed under 1c.
2.1 Select, appraise and prepare subproject summary reports for candidate subprojects [GCD].
Sub-projects preparation. Ambon: CW6 (CW7, CW8, CW9 w/o SSR). Banten: CW10 (CW11, CW12, CW13 w/o SSR).
8 units
8 units
MPWH, CS01
Q4 2022
Sub-project appraisal (Design and EE). Ambon: CW6 by July 2021.
Sub-project appraisal (Design and EE). Ambon: CW7, CW8, CW9 by July 2022.
SSR CW6 and CW10 are under process. Other CWs no need SSR.
2C
2a. Flood protection infrastructure rehabilitated or upgraded as per FRMPs developed.
2.2 Prepare DEDs for the selected subprojects, including environmental and social safeguards documents and tender documents [KNS].
CW1
1 Unit
1 Unit
MPWH, CS01
Q1 2018
Designed.
Revised design and bidding.
Contracted on 5 Dec 2019.
Completed.
2C
2a. Flood protection infrastructure rehabilitated or upgraded as per FRMPs developed.
2.2 Prepare DEDs for the selected subprojects, including environment and social safeguards documents and tender documents [KNS].
CW2
1 Unit
1 Unit
MPWH, CS01
Q1 2018
Designed.
Revised design and bidding.
Contracted on 5 Dec 2019.
Completed.
2C
2a. Flood protection infrastructure rehabilitated or upgraded as per FRMPs developed.
2.2 Prepare DEDs for the selected subprojects, including environmental and social safeguards documents and tender documents [KNS].
CW3
1 Unit
1 Unit
MPWH, CS01
Design in Mar 2020. Bidding in Aug 2020.
Contracted on 3 Feb 2021.
Completed.
2C
2a. Flood protection infrastructure rehabilitated or upgraded as per FRMPs developed.
2.2 Prepare DEDs for the selected subprojects, including environment and social safeguards documents and tender documents [KNS].
CW4A
1 Unit
1 Unit
MPWH, CS01
Designed.
Revised design and bidding.
Contracted on 30 Mar 2020.
Completed.
2C
2a. Flood protection infrastructure rehabilitated or upgraded as per FRMPs developed.
2.2 Prepare DEDs for the selected subprojects, including environmental and social safeguards documents and tender documents [KNS].
CW4B
1 Unit
1 Unit
MPWH, CS01
Designed.
Bidding in Mar 2021. Contracted on 26 Aug 2021. Physical Progress at the end of December 2021 3,65%.
The mayor of Ambon issued a Decree on Logging on 29 December 2021.
2D
2a. Flood protection infrastructure rehabilitated or upgraded as per FRMPs developed under 1c.
2.3 Implement LAR and civil works for candidate subprojects [GCD].
CW1, CW2, CW3, CW4A, CW4B.
5 units
5 units
MPWH, CS01
Physical Progress: CW1 29.36%, CW2 34.48%.
Physical Progress: CW1 68.43%, CW2 55.55%, CW4A 42.80%.
Physical Progress: CW1 77.31%, CW2 76.192%, CW3 2,520%, CW4A 100% (Nov), CW4B 0.904%.
Physical Progress: CW1 98.054%, CW2 96.299%, CW3 24.630%, CW4A 100% (Nov), CW4B 37.260%.
Physical Progress by September 2024. CW1 100% (done), CW2 100% (done), CW3 100% (done), CW4A 100% (done), CW4B 100% (done).
2D
2a. Flood protection infrastructure rehabilitated or upgraded as per FRMPs developed under 1c.
2.4 Construct check dams and small retention ponds.
CW4A, CW4B
2 units
2 units
MPWH, CS01
CW4A was COMPLETED on November 2021.
CW4B target finished in 2023.
2D
2b. River O&M manual and plans for flood protection infrastructure endorsed by DGWR.
2.5 Prepare River O&M manual and plans [GCD].
CW1, CW2, CW3, CW4A, CW4B
5 units
5 units
MPWH, CS01
Q4 2020
3A
3a. Guidelines for CBFRM prepared.
3.1 Prepare CBFRM guidelines [GCD, GEM].
CBFRM Guidelines
18 documents
18 documents
MOHA, CS06
Q3 2018
Draff CBFRM Guideline.
CBFRM Guideline is applicable.
MOHA developed 45 guidelines and technical instructions for the CBFRM activities, emphasizing slope stabilization and urban flood protection in Ambon City.
There are already 45 guidelines for CBFRM.
3A
3b. 30 communities in the Ambon-Seram and Cidanau-Ciujung-Cidurian RBTs have access to information from flash flood localized early warning system.
3.2 Identify and establish CBRFM groups and provide capacity development [GCD, GEM].
KMSB
30 KMSB
140 KMSB
MOHA, CS06
Q4 2018
Total (7): Ambon (7), Serang (0), Lebak (0), Pandeglang (0).
Total (125): Ambon (21), Serang (46), Lebak (48), Pandeglang (10).
Total (15): Ambon (0), Serang (2), Lebak (13), Pandeglang (0).
The CAPs of KMSB were completed with drawings and budget, coordinated with Bappeda, and integrated with the OPD program.
Total KMSB (140): Ambon (21) Serang (48) Lebak (61) Pandeglang (10)
3A
3c. CBFRM programs implemented.
3.3 Formulate community-based measures to reduce flood risk [GEM].
CBFRM implementation
MOHA, CS06
CBFRM implementation started in 2020 with community group training. Survey, Investigation, and Design (SID) for the proposed activities have been conducted.
3A
3c. CBFRM programs implemented.
3.4 Prepare contingency plans and standard operating procedures [GEM]. (6 training x 4 districts = 24 training).
Community training
24 trainings
24 trainings
MOHA, CS06
Q2 2019
Already carried out 24 training activities.
3A
3c. CBFRM programs implemented.
3.5 Support community participation in the design of community-based infrastructure [GEM].
Community participation
MOHA, CS06
3A
3c. CBFRM programs implemented.
3.6 Supervise the construction of community-based infrastructure and prepare O&M plans [GEM].
Small-infrastructure
248 activities
248 activities
MOHA, CS06
Q3 2018
Ambon: Urban drainage (16)
Serang: Participatory design (10). Lebak: Drainage construction (4).
Serang: Drainage (13), Evacuation path (3), Planning design (26). Lebak: Drainage (61), Planning design (4).
Serang: Drainage (25), Evacuation path (4), Planning design (8). Lebak: Drainage (19). Pandeglang: Drainage (33), Supervision (5).
Serang: Drainage (12), Evacuation path (3). Lebak: Drainage (29). Pandeglang: Drainage (19), Supervision (10). Ambon: Evacuation path (3).
Total activities (307): Drainage (231), Evacuation paths (13), Planning design (48), Supervision (15).
3A
3d. At least 30% of those involved in the identification and design of community-level infrastructure and O&M are female.
3.5 Support community participation in the design of community-based infrastructure [GEM].
Including 30% of women
MOHA, CS06
Q4 2022
Banten, Women: 30% ON TRACK. Maluku, Women: 26%.
Maluku, Women: 18%.
There are 527 people involved in the identification, prioritization, and design of community-level infrastructure: Pandeglang 299 (32%), Serang 259 (40%), Lebak 406 (23%), Ambon 170 (22%). Gender-responsive disaster contingency plans will be formulated this year.
3A
3e. Contingency plans are gender-responsive.
3.5 Support community participation in the design of community-based infrastructure [GEM].
CBFRM training
MOHA, CS06
Q4 2022
CBFRM groups operationalized in December 2019.
Contingency plans were integrated into the city and district work plans in 2020.
Training on CBFRM (under output 3, GAP Target 9), benefited 3,117 people trained, of which 765 are women (24.54%).
4A
4a. GIS-based M&E system established.
4.1 Prepare the M&E framework [GCD].
M&E framework
MPWH, CS02
Q4 2021
GIS-based M&E system has been developed for MOA, MOHA, and MPWH.
4A
4a. GIS-based M&E system established.
4.2 Develop the GIS-based M&E system [GCD].
M&E GIS-based
1 unit
1 unit
MPWH, CS02
Q4 2018
4 thematic maps: (i) location maps of CW1 and CW2, (ii) CW1 and CW2 land parcel maps, (iii) proposed 2018 farmer groups and location maps, and (iv) village target to flooding maps of Ring 1 and 2.
4 thematic maps: (i) proposed 2019 farmer groups and location maps, (ii) KMSB locations and FG locations of 2019 small-scale infrastructures development, (iii) CW1 and CW2 physical progress, and (iv) location of the hydro-meteorology stations.
5 thematic maps: (i) KMSB locations of 2020 small-scale infrastructures development, (ii) FG locations of 2020 small-scale infrastructures development, (iii) physical progress maps of Petra and Yakobus check dam, (iv) flood-prone maps, and (v) flood model maps.
4 thematic maps: (i) KMSB locations of 2021 small-scale infrastructures development activities, (ii) FG locations of 2021 small-scale infrastructures development activities, (iii) physical progress maps of Petra and Yakobus check dam, and (iv) location of the hydro-meteorology stations.
4 thematic maps: (i) KMSB locations of 2021 small-scale infrastructures development activities, (ii) FG locations of 2021 small-scale infrastructures development activities, (iii) physical progress maps of Petra and Yakobus check dam, and (iv) location of the hydro-meteorology stations.
4 thematic maps: (i) Locations of small-scale infrastructure activities for KMSB in 2022. (ii) Locations of small-scale infrastructure activities for FG in 2022. (iii) LARP maps of CW1, CW2, CW3 in 2023. (iv) Locations of hydro-meteorology stations in 2023.
4B
4b. A national strategy and corresponding guidelines to institutionalize the FRM approach approved by the NSCWR and National Water Council.
4.3 Prepare the national strategy and guidelines to institutionalize the FRM approach [GCD].
National FRM
1 document
1 document
BAPPENAS, CS04
Q4 2022
CS04 recruitment process.
CS04 mobilization.
National FRM strategy discussion on 12 April 2021.
The draft National FRM Strategy for finalization in Q4 2022.
4B
4b. A national strategy and corresponding guidelines to institutionalize the FRM approach approved by the NSCWR and National Water Council.
4.4 Provide technical capacity building for relevant agencies [GCD, GEM].
Technical capacity building
BAPPENAS, CS04
4B
4c. Corresponding guidelines to institutionalize the FRM approach approved by the NSCWR and National Water Council.
4.5 Ensure coordination among project stakeholders [GEM].
ADB Mission
4 meetings
4 meetings
BAPPENAS, CS04
Q4 2022
ADB Mission March 2018. MoU 2018 produced.
ADB Mission July 2019. MoU 2019 produced.
ADB Mission June 2020. MoU 2020 produced.
ADB Mission April 2021. MoU 2021 produced.
ADB Mission September-October 2022. MoU 2022 produced.
ADB Mission July-August 2023. MoU 2023 produced.
Records : 43 of 43